Project Timeline


April 2009 Voters approve Master Plan for CCHS
April 2010      
Voters approve Feasibility Study and Schematic Design for CCHS
Sept.  2010        
CCHS is invited to participate in the Massachusetts School Building Authority's program for reimbursement
June 2011 Feasibility study completed
Aug. 16, 2011
Schematic Design completed and approved by CCHS Building Committee
Aug. 19, 2011 Schematic Design is submitted to MSBA for approval
Sept. 28, 2011            
MSBA Board meets and approves CCHS project for funding
Nov. 2011
                       
The towns of Concord and Carlisle vote and overwhelmingly approve CCHS project at Town Meetings and polls
Early 2012 Work begins on Detailed Design, Construction Manager is hired
Aug. 2012 Detailed Design complete, work begins on construction drawings, early bid packages prepared
Fall 2012
Construction begins
Fall 2015      
Building ready for occupancy
Late 2015 Site work complete


 
 
 
 