April 2009 |
Voters approve Master Plan for CCHS |
April 2010
|
Voters approve Feasibility Study and Schematic Design for CCHS
|
Sept. 2010
|
CCHS is invited to participate in the Massachusetts School Building Authority's program for reimbursement |
June 2011 |
Feasibility study completed |
Aug. 16, 2011
|
Schematic Design completed and approved by CCHS Building Committee
|
Aug. 19, 2011 |
Schematic Design is submitted to MSBA for approval |
Sept. 28, 2011
|
MSBA Board meets and approves CCHS project for funding |
Nov. 2011
|
The towns of Concord and Carlisle vote and overwhelmingly approve CCHS project at Town Meetings and polls
|
Early 2012 |
Work begins on Detailed Design, Construction Manager is hired
|
Aug. 2012 |
Detailed Design complete, work begins on construction drawings, early bid packages prepared
|
Fall 2012
|
Construction begins
|
Fall 2015
|
Building ready for occupancy
|
Late 2015 |
Site work complete
|